● The connection between two networks to form an internet is handled by a machine known as a__(71)__.
(71)A.bridge
B.client
C.router
D.switch
● One tool that is useful during both analysis and design is the__(72)__,which is a pictorial representation of the items of information(entities) within the system and the relationships between these pieces of information.
(72)A.data dictionary
B.dataflow diagram
C.use case diagram
D.entity-relationship diagram
●
()is one of the techniques used for estimating activity durations.
(73)A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. __(74)__is following the process- Estimate Activity Durations.
(74)A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
● __(75)__is not the tool name for quality controlling used in the figure below.
(75)A.Cause and Effect Diagrams
B.Ishikawa Diagrams
C.Fishbone Diagrams
D.Scatter Diagram