● Most of the host operating system provides a way to automated configure the IP information needed by a host. Automated configuration methods, such as __(71)__ ,are required to solve the problem.
(71)A.IPSec
B.DHCP
C.PPT
D.SOAP
● hich factors must be most considered when developing acceptance creteria?__(72)__
(72)A.Match with requirements
B.User availability
C.Ablity to benchmark system
D.Schedule of system delivery
● Many useful tools techniques are used in developing schedule. __(73)__s a schedule network analysis technique that modifies the project schedule to account for limited resource.
(73)A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain method
● In all projects, needs must be tempered by schedule , cost and resource constraints. Project success depends primarily on __(74)__。
(74)A.The quality of the schedule and cost control analysis
B.Customer satistaction
C.Cuctomer compromise in defining its needs
D.Exceeding customer requirements through gold-plating
● __(75)__ is one of the quality planning outputs.
(75)A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist