试题71-命-技-N.ZJ.00.p000-9.00-质量规划工具通Quality planning tools are often used to help plan effective quality management activities .(71) is one of such tools, which involves comparing actual or planned project practices to other projects to generate ideas for i
<尚大教育,教育至上,人才为大:sdedu.cc>
试题71-命-技-N.ZJ.00.p000-9.00-质量规划工具通
Quality planning tools are often used to help plan effective quality management activities .(71) is one of such tools, which involves comparing actual or planned project practices to other projects to generate ideas for improvement and to provide a basis by which to measure performance. (71)A、Benchmarking B、Quality metric C、Quality checklist D、Brainstorming
试题72-命-技-N.ZJ.00.p000-9.00-组合
A_(72) is a collection or projects and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives.
(72)A、program B、portfolio C、project of large size D、PMO
试题73-命-技-N.ZJ.00.p000-9.00-沟通渠道
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communications. According to Metcalfe’s Law, a project with 10 stakeholders has (73) potential communication channels.
(73)A、10 B、45 C、50 D、100
试题74-命-技-N.ZJ.00.p000-9.00-风险应对策略
There are strategies typically deal with threats or risks that may have negative impacts on project objectives if they occur. Some other strategies are suggested to deal with risks with potentially positive impacts.(74) is a risk response strategy that may be adopted for either threats or opportunities.
(74)A、Share
B、Mitigate C、Transfer D、Acceptance
试题75-命-技-N.ZJ.00.p000-9.00-政府采购
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the (75) and the procuring agencies.
(75)A、users B、servers C、producers D、suppliers