【信监1811】试题71 () techniques are used to find ways to bring project activities that are behind int
71、() techniques are used to find ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing the schedule for the remaining work .A 、 Schedule forecasts
B 、Schedule compression
C 、Change requests
D 、D