74、estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including( ).
A、expert judgment B、analogous estimating
C、requ
<尚大教育,教育至上,人才为大:sdedu.cc>
74、estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including( ).
A、expert judgment B、analogous estimating
C、requirements traceability matrix D、three-point estimating