● Risk management allows the project manager and the project team not to__(71)__.
(71)A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
● The project life-cycle can be described as __(72)__.
(72)A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
● __(73)__is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.
(73)A.PERT
B.AOA
C.WBS
D.PDM
● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved __(74)__ that can serve as a baseline to track progress.
(74)A.scope statement
B.activity list
C.project charter
D.project schedule
● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a __(75)__ .
(75)A.Project Scope Statement
B.Project Management Plan
C.Forecasts
D.Project Charter