2011年下半年 系统集成项目管理工程师 上午试卷(71-75)
来源:尚大教育 作者:尚大教育 时间;2018-12-07 11:55:38 点击数: 尚大软考交流群:376154208
试题71-命-管-N.ZJ.00.p000-1.00-The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project. The project manager maintains this link through (71).
A.periodic project reports, perio
<尚大教育,教育至上,人才为大:sdedu.cc>

试题71-命-管-N.ZJ.00.p000-1.00-

The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project. The project manager maintains this link through (71).
A.periodic project reports, periodic visits to the customer, and telephonic exchanges
B.subordinates, project team members, and the project sponsor
C.one-time reports, weekly reports, and monthly reports
D.the telephone, facsimile, and data transmission
 
 

试题72-命-管-N.ZJ.00.p000-1.00-

A proj ect manager is called to an informal meeting with the customer and a problem is raised. Thisproblem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager should (72)
A.tell the customer that he will not address any problems becausethis is only an information exchangemeetmg
B.ell the customer that the problem is not sufficiently defined to determine the appropriate action
C.ollect as much information on the problem without committing his company to a solution
D.give the customer a range of solutions that might be acceptable to his Company
 
 

试题73-命-管-N.ZJ.00.p000-1.00-

The project schedule is more than a document that lays out the activities over time to representthe time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .
A.measure, delay, record, distribute, analyze, and direct
B.plan, schedule, monitor, control, report, and forecast
C.promote, highlight, monitor, control, forecast, and report
D.emphasize, visualize, analyze, conceptualize, report, and record
 
 

试题74-命-管-N.ZJ.00.p000-1.00-

Which of the following Project Scope Management processes involves subdividing the majorproject deliverables into smaller, more manageable components? (74)
A.Scope Planning B.Scope Verification
C.Scope Change Control D.Scope Definition
 
 

试题75-命-管-N.ZJ.00.p000-1.00-

The work breakdown structure comprises several levels of decomposition of the total project.The lowest level of definition is always the (75).
A..pµlanning B.element C.subtask D.working interface
 
 
<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:2011年下半年 系统集成项目管理工程师 上午试卷(61-70)
下一篇: 2012年上半年 系统集成项目管理工程师上午试题(1-10)
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章