试题71-命-技-N.ZJ.00.p000-22.0A test case normally consists of a unique identifier, requirement references from a design specification, events, a series of steps to follow, input, output, actual result, and (71) 。
A. bug
B. expected result
C. test rep
<尚大教育,教育至上,人才为大:sdedu.cc>
试题71-命-技-N.ZJ.00.p000-22.0
A test case normally consists of a unique identifier, requirement references from a design specification, events, a series of steps to follow, input, output, actual result, and (71) 。
A. bug
B. expected result
C. test report
D. traceability matrix
试题72-命-技-N.ZJ.00.p000-22.0
The Systems Development Life Cycle (SDLC) is a process of creating or altering information systems, and the models and methodologies that people use to develop these systems. Sequential SDLC models, such as (72), focus on complete and correct planning to guide large projects and risks to successful and predictable results.
A. Waterfall
B. Extreme Programming
C. Spiral
D. Rapid Prototyping
试题73-命-技-N.ZJ.00.p000-22.0
Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73) .
A. project management plan
B. project baseline
C. risk response plan
D. risk baseline
试题74-命-技-N.ZJ.00.p000-22.0
The project budget has been finalized. Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.
A. Contingency reserve
B. Project profit
C. Management reserve
D. Special fund
试题75-命-技-N.ZJ.00.p000-22.0
Several risk response strategies are available. (75) the risk simply gives another partly responsibility for its management, it does not eliminate risk.
A. Avoiding
B. Mitigating
C. Accepting
D. Transferring
<尚大教育,教育至上,人才为大:sdedu.cc>