2012年下半年 系统集成项目管理工程师上午试题(71-75)
来源:尚大教育 作者:尚大教育 时间;2018-12-10 09:24:10 点击数: 尚大软考交流群:376154208
试题71-命-技-N.ZJ.00.p000-22.0A test case normally consists of a unique identifier, requirement references from a design specification, events, a series of steps to follow, input, output, actual result, and (71) 。
A. bug
B. expected result
C. test rep
<尚大教育,教育至上,人才为大:sdedu.cc>

试题71---N.ZJ.00.p000-22.0

A test case normally consists of a unique identifier, requirement references from a design specification, events, a series of steps to follow, input, output, actual result, and  (71) 。  
A. bug
B. expected result  
C. test report
D. traceability matrix

试题72---N.ZJ.00.p000-22.0

The Systems Development Life Cycle (SDLC) is a process of creating or altering information systems, and the models and methodologies that people use to develop these systems. Sequential SDLC models, such as (72), focus on complete and correct planning to guide large projects and risks to successful and predictable results.
A. Waterfall
B. Extreme Programming    
C. Spiral
D. Rapid Prototyping

试题73---N.ZJ.00.p000-22.0

Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73) .
A. project management plan  
B. project baseline  
C. risk response plan  
D. risk baseline

试题74---N.ZJ.00.p000-22.0

The project budget has been finalized. Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.
A. Contingency reserve  
B. Project profit   
C. Management reserve   
D. Special fund

试题75---N.ZJ.00.p000-22.0

Several risk response strategies are available. (75) the risk simply gives another partly responsibility for its management, it does not eliminate risk.
A. Avoiding    
B. Mitigating   
C. Accepting   
D. Transferring
 
<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:2012年下半年 系统集成项目管理工程师上午试题(61-70)
下一篇:2013年上半年 系统集成项目管理工程师上午试题(1-10)
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章