71、WLAN is increasingly popular because it enables cost-effective () among people and applications that were not possible in the past.
A、line B、circuit C、connection D、Interface

72、()is not included in the main
<尚大教育,教育至上,人才为大:sdedu.cc>
71、WLAN is increasingly popular because it enables cost-effective () among people and applications that were not possible in the past.
A、line               B、circuit              C、connection               D、Interface
 
72、()is not included in the main contents of the operation and maintenance of the  information system.
A、Daily operation and maintenance                   B、System change
C、Securitymanagement                                         D、Business change
 
73、In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.
A、Activity list                              B、Work Breakdown Structures
C、Activity Attributes                            D、Milestone Lists
 
74、The customer asks your project to be completed 6 months earlier than planned、You think this target can be reached by-overlapping project activities. This approach is known as ().
A、balance engjneering       B、fast-tracking        C、leveling                  D、Crashing
 
75、The auditing function that provides feedback about the quality of output is referred to as ().
A、quality control                                B、quality planning
C、quality assurance                           D、quality improvement
 
 
 
 
 
 
<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇: 2016年5月 系统集成项目管理工程师 上午试卷(61-70)
下一篇:2016年下半年 系统集成项目管理工程师上午试题(1-10)
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章