71、WLAN is increasingly popular because it enables cost-effective () among people and applications that were not possible in the past.
A、line B、circuit C、connection D、Interface
72、()is not included in the main
<尚大教育,教育至上,人才为大:sdedu.cc>
71、WLAN is increasingly popular because it enables cost-effective () among people and applications that were not possible in the past.
A、line B、circuit C、connection D、Interface
72、()is not included in the main contents of the operation and maintenance of the information system.
A、Daily operation and maintenance B、System change
C、Securitymanagement D、Business change
73、In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the project deliverables. ()are not output of activity definition.
A、Activity list B、Work Breakdown Structures
C、Activity Attributes D、Milestone Lists
74、The customer asks your project to be completed 6 months earlier than planned、You think this target can be reached by-overlapping project activities. This approach is known as ().
A、balance engjneering B、fast-tracking C、leveling D、Crashing
75、The auditing function that provides feedback about the quality of output is referred to as ().
A、quality control B、quality planning
C、quality assurance D、quality improvement