73、Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. ( ) process does not belong
<尚大教育,教育至上,人才为大:sdedu.cc>
73、Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. (  ) process does not belong to Project Integration Management.
    A、Developing project charter    B、Developing project management plan 
    C、Analyzing project risks       D、Monitoring and controlling project
尚大教育-参考答案:
 
<尚大教育,教育至上,人才为大:sdedu.cc>
 
   各省软考办 
 
来顶一下
返回首页
返回首页
上一篇:【中项1805】试题72
下一篇:【中项1805】试题74
 相关文章
 
 
跟贴共
笔 名 :   验证码:
网友评论仅供其表达个人看法,并不表明尚大教育同意其观点或证实其描述
距离2023年05月27-28日软考考试还有
尚大软考交流群:376154208
软考各地考务机构
历年真题汇总




各省市软考报名简章