75、If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and( ) of the project management plan are revised and reissued to reflect the approved changes
A、developing baselines B、testing baselines
C、schedule baselines D、ending baselines
尚大教育分析:
如果一个批准的变更对项目范围有影响,那么相关的文档以及项目管理计划中的成本基线和()就要进行修订和更新,以反映这个变更。
A、开发基线 B、测试基线
C、进度基线 D、收尾基线
尚大教育参考答案:C